Underpinning logo

Common methods of basement excavation

Basement excavation is the process of digging out the ground beneath a building to create a basement or sub-basement level. This involves the removal of soil, rock, or other materials to create a space suitable for the construction of a foundation and the installation of underground utilities. Basement excavation is often required when building on a site with limited space or when additional space is needed for storage or living areas. It can also be used to lower the foundation of an existing building to create more headroom or to improve access to underground utilities. The process of basement excavation can be complex and involves careful planning to ensure workers’ safety and the building’s stability. It may require heavy equipment such as excavators, bulldozers, and cranes and may involve shoring and bracing to prevent cave-ins and other hazards. Several methods can be used for basement excavation, some mentioned below.

The Open-Cut Method:

The open-cut method for basement excavation is one of the most common and traditional excavation methods. It involves digging a trench or pit in the ground to the desired depth and then constructing the basement within it. The excavated soil is then removed from the site or stored on site until it is needed for backfilling. Here are the steps involved in the open-cut method for basement excavation:

  1. Site Preparation: The site is cleared of existing structures or debris, and the area where the excavation will occur is marked out.
  2. Excavation: The soil is excavated using mechanical equipment such as excavators, backhoes, or bulldozers. The excavation is done in stages, with the soil being removed to the required depth.
  3. Shoring: Once the excavation is complete, the trench walls are shored up to prevent collapse. This can be done using timber or steel props, sheet piles, or shotcrete.
  4. Basement Construction: The basement is constructed within the trench, usually using concrete or masonry blocks. The floor is generally made of reinforced concrete.
  5. Backfilling: Once the basement is constructed, the excavated soil is used to backfill around the basement walls. This helps to provide additional support to the walls and prevent water from seeping in.
  6. Site Restoration: The site is restored by removing any temporary structures, cleaning up debris and excess soil, and preparing the site for further construction or landscaping.

The open-cut method is generally more suitable for larger projects with sufficient space for the excavation equipment and where the site is relatively flat.

The Top-Down Method:

The top-down method for basement excavation is a popular approach when constructing basements in urban areas where space is limited and there is a need to minimize disruption to surrounding buildings and infrastructure. In this method, the basement is constructed from the top down, starting with the roof slab and working downwards.

Here are the steps involved in the top-down method for basement excavation:

  1. Site Preparation: The site is cleared, and the area where the excavation will occur is marked out.
  2. Excavation: The top layer of soil is excavated to the depth of the basement floor slab. This excavation is done in sections, with each area being excavated and then backfilled with a suitable material to provide a stable working platform.
  3. Slab Construction: Once the first layer of soil is excavated, a reinforced concrete slab is constructed, which serves as the base for the basement. This slab is constructed in sections, and each section can cure before the next section is constructed.
  4. Shoring: Once the first slab is in place, the basement walls are shored up using a temporary support system such as steel beams, props or shotcrete.
  5. Excavation of Next Level: Once the walls are shored up, the excavation continues downwards to the next level, and the process is repeated until the desired depth is reached.
  6. Construction of Permanent Walls and Floors: Once the excavation is complete, the permanent basement walls and floor slab are constructed. The temporary support system is removed, and necessary finishing works are completed.
  7. Site Restoration: The site is restored by removing any temporary structures, cleaning up debris and excess soil, and preparing the site for further construction or landscaping.

The top-down method is generally more suitable for sites where space is limited and the excavation depth is shallow to moderate. It is essential to consult with a professional engineer or contractor to determine the best method for your specific project.

Bracing Method for Basement Excavation

  1. Bracing: Bracing is a standard method for supporting the walls of excavation during basement construction. Bracing is necessary to prevent the walls from collapsing or moving, which could cause damage to adjacent structures or pose a safety risk to workers on the site. There are several different types of bracing methods used in basement excavation, including:
  2. Timber Shoring: This is one of the oldest and simplest forms of bracing. It involves installing horizontal timber boards, called walers, along the length of the excavation and vertical timber posts, called struts, at regular intervals to support the boards. The walers and struts are bolted or nailed together to create a stable structure.
  3. Soldier Pile and Lagging: This method involves installing vertical steel or concrete beams, called soldier piles, along the perimeter of the excavation at regular intervals. Horizontal timber planks, called lagging, are inserted between the soldier piles to create a wall. The lagging is usually held by steel or timber ties anchored to the soldier piles.
  4. Sheet Piling: This method involves installing interlocking steel or concrete sheets along the perimeter of the excavation. The sheets are driven into the ground using hydraulic hammers or vibratory equipment. Once the sheets are in place, the soil is excavated inside the perimeter, and the sheet piles support the excavation.
  5. Shotcrete: This method involves spraying a mixture of concrete and water onto the excavation walls to create a thick, reinforced layer of concrete. The shotcrete is usually applied to a temporary support system, such as steel mesh or wire, anchored to the excavation walls.

The choice of bracing method will depend on factors such as the depth and size of the excavation, the soil conditions, and the surrounding structures. It is essential to consult with a professional engineer or contractor to determine the most appropriate bracing method for your specific project.

Anchored Method for Basement Excavation

The anchored method is a commonly used bracing method for basement excavation. It involves installing an anchored system to support the excavation walls and prevent them from collapsing or moving. The anchored system consists of a series of steel rods, called tiebacks, installed through the excavation wall and anchored into the surrounding soil or rock.

Here are the steps involved in the anchored method for basement excavation:

  1. Site Preparation: The site is cleared, and the area where the excavation will occur is marked out.
  2. Excavation: The top layer of soil is excavated to the depth of the basement floor slab. This excavation is done in sections, with each area being excavated and then backfilled with a suitable material to provide a stable working platform.
  3. Wall Construction: Once the first layer of soil is excavated, the basement walls are constructed using reinforced concrete or other suitable materials.
  4. Anchor Installation: After the walls are constructed, holes are drilled through the walls at regular intervals. Steel tiebacks are then inserted into the holes and anchored into the surrounding soil or rock using grout or other suitable anchoring materials.
  5. Bracing: Once the tiebacks are installed, a temporary support system, such as steel beams or wood frames, is installed to support the excavation walls.
  6. Excavation of the Next Level: Once the temporary support system is in place, the excavation continues downwards to the next level. The process is repeated until the desired depth is reached.
  7. Wall Finishing: Once the excavation is complete, any necessary finishing work is completed on the basement walls, such as waterproofing or insulation.
  8. Site Restoration: The site is restored by removing any temporary structures, cleaning up debris and excess soil, and preparing the site for further construction or landscaping.

The anchored method is generally more suitable for sites with limited space, and the excavation depth is moderate to profound. It is essential to consult with a professional engineer or contractor to determine the best method for your specific project.

Island Method for Basement Excavation

The Island Method is a bracing method used for basement excavation in situations where the adjacent structures or buildings are sensitive to vibrations or if there is a risk of damage to the surrounding buildings. This method involves excavating the centre of the area and leaving a perimeter of soil around the excavation area to act as a natural support system for the excavation walls. Here are the steps involved in the Island Method for basement excavation:

  1. Site Preparation: The site is cleared, and the area where the excavation will occur is marked out.
  2. Excavation of the Centre: The centre of the excavation area is excavated to the required depth for the basement.
  3. Perimeter Excavation: Once the centre is excavated, the perimeter of the excavation area is excavated in small sections. The depth of the perimeter excavation is usually shallow, and it is kept to a minimum to ensure that the perimeter soil acts as a natural support system.
  4. Wall Construction: Once the excavation is complete, the basement walls are constructed using reinforced concrete or other suitable materials.
  5. Bracing: Once the walls are constructed, a temporary support system, such as steel beams or wood frames, is installed to support the excavation walls.
  6. Excavation of the Next Level: Once the temporary support system is in place, the excavation continues downwards to the next level. The process is repeated until the desired depth is reached.
  7. Wall Finishing: Once the excavation is complete, any necessary finishing work is completed on the basement walls, such as waterproofing or insulation.
  8. Site Restoration: The site is restored by removing any temporary structures, cleaning up debris and excess soil, and preparing the site for further construction or landscaping.

The Island Method is generally more suitable for sites with limited space and where adjacent structures or buildings are sensitive to vibrations or damage. It is essential to consult with a professional engineer or contractor to determine the best method for your specific project.

Table of Contents